The consultation program focuses on updating guidelines and procedures to support power system security, market operations and the Territory Electricity Market reforms. Themes include market interactions, scheduling and dispatch, battery energy storage systems (BESS) and Secure System Guidelines.

Market Operator

March - July 2025

Market interactions enablement and initial MSATS implementation (standard consultation)

September - October 2025

Planned follow-up consultation on Market Interactions Enablement and MSATS updates deferred to early 2026.

Late 2025 (October - December)

Ongoing review and update of NTESMO website structure & content

March - September 2026

Market Operations Procedures: Minor review and update of existing procedures (consultation package forthcoming)

April - June 2026

Market Interactions Enablement: Develop market procedures supporting MSATS.

September - November 2026

Further Market Interactions updates (expedited/minor consultations)

Power System Controller (PSC)

January - October 2025

Secure System Guidelines (SSG) Version 5 amendments (expedited consultation).

1 November 2025

Secure System Guidelines (SSG) Version 5 effective
Version 5 of the SSG commenced following an expedited consultation process.

3 November 2025

Scheduling and Dispatch procedural review – discussion paper released
Initiates the consultation on a consolidated scheduling and dispatch procedure.

November - December 2025

Scheduling & Dispatch procedural review
NTESMO reviews submissions received from a retailer and generator licensees.
Feedback informs next-stage procedural drafting.

November 2025 - July 2026

Review and amendment of Scheduling and Dispatch procedures, including consolidation of the Tie-Break Procedure and the Dispatch and Pricing Procedure.

Early 2026

Follow-up consultation on Scheduling and Dispatch amendments (part of Nov 2025–Jul 2026 program).

February - November 2026

Grid-connected BESS Guidelines
Standard consultation covering connection requirements and operational considerations.

June - November 2026

Secure System Guidelines (SSG) Version 6
Comprehensive review (excluding frequency control), including contingency definitions and minor procedural updates.

Network Service Provider  (NSP)

2026

Grid-scale storage and Territory Electricity Market (TEM) reform alignment
Consultation timing contingent upon NT Government policy schedule.

November 2025 - 21 January 2026

Small-scale battery energy storage systems (BESS) (≤2 MW) technical connection consultation
Licensed NSP consultation on connection/specification requirements.